fitches
Back to Chronicles.
![]() |
![]() |
Photos above by Dick Wilson, December 20, 2001
Delhi, NY - Fitches Bridge Restoration Nears Completion.
Thursday, Nov. 1, 2001 - Hi Everyone! I thought you might enjoy seeing some new
photos on the progress made on the Fitches Covered Bridge - NY-13-02. These were taken on
October 28th.
Doesn't it look fantastic? As you will see, windows
were added, as in the Hamden Covered Bridge, to allow for kids to fish and hopefully less
destruction to the bridge.
Trish Kane




Delhi, NY - Fitches Bridge Restoration Underway.
Thursday, 13 Sep 2001 - The Bridge Stands on its Own
Hi Joe: The column supports from the steel frame are released and the bridge is now setting on its
own, albeit on temporary blocks. Note the missing rafters over the steel column bent that has to
be retrieved up through the structure.
The end view with frames shows a close up of the
support system and the rebuilt ends of the trusses.
The photo of the upper framing shows the strong
bracing system, and authentic use of pegs and traditional wedges with upper laterals.
The last photo is of the jacking operation, depicting
the single hydraulic jack used at each corner to raise the bridge. Not a sound of distress from the
bridge during the operation. --Phil




Sunday, 10 Jun 2001 - Hi Joe - thought it was time for a brief update on Fitch's
Bridge.



We have identified the lattice members that have to be replaced due primarily to deterioration
in the lower bottom chord connections (I have just taken a bunch of photos of these conditions
and will forward on later). Due to the surprise with the critter home in the top chord, we will
separate all of the top chord pairs looking for other surprises.
We have the first and large load of
timber on hand, but have had to order twice more for the new surprises. We will be focusing on
repair of the upstream truss first in its entirety while we await delivery of the remaining timbers
which will allow us to finish both trusses.
Due to major powder post beetle
damage in the trunnels, we have ordered replacements for all of them. We are using glue-lam floor
beams that should be delivered shortly. Slow going what with all of the other project interruptions
ongoing around the County. We are still on target for completion by the fall.
As always, I'm here to respond to
queries - I would much prefer to answer questions, rather than have questions go unanswered or
be the subject of speculation. Thanks, Phil Pierce
Monday, 11 Jun 2001 - Joe - three more photos to add to the last.



As of today, the guys installed the first new members in the old truss. The rebuilding is now underway. Phil
Wed, 21 Feb 2001
Fitches Bridge, Delhi, NY - So we're off and running with the rehabilitation of the
Fitches
Covered Bridge. We have removed a couple of patches of the roof and floor to allow the
placement of steel piles down through the structure to help support an internal steel support
frame. Two main beams have been installed in the "belly" of the bridge and rest on columns in the
approach embankment at each end of the bridge and on the center pile "bent". (I was unwilling to
have us buy two extremely heavy and long steel beams in an attempt to avoid the center bent -
that would have been very expensive just for this purpose - the "two-span" temporary structure
serves just as well and used scrap material that we already owned.) The main beams are connected
with bracing and cables for stability. They support a pair of transverse steel box beams (old
pieces of box beam guide railing) at about 12 foot spacing.
Fitches Bridge interior. Photo taken early in the
work.→
Photo taken from Route 10 early in the work →
Friday, 9 Mar 2001
Fitches Bridge, Delhi, NY - Hi Joe [here are] a couple of photos for Fitches related to
the testing we did just before beginning the rehabilitation work. The platform was needed to
allow access directly to the bottom chord. The other shows some of the myriad of wires and
gauges - quite a rat's nest.
Platform for BDI testing
→
Friday, 23 Mar 2001
Good Morning, Vermont!
We had a nice break in the weather here in New York last weekend (March 18) so Bob and I
ventured out to see the restoration work being done on the Fitches Covered Bridge. Here are a
few photos for you. We also stopped by the Hamden bridge. It really looks terrific and it was a
great day for photographs. Hope you enjoy them, Joe.
Warmly, Bob and Trish





Fitches Bridge, a Town Truss span of 100 feet, crosses the West Branch of the Delaware River. It was built in 1870 by James Frazier and James Warren three miles downstream from its present location. It was moved in 1885 to where it can be reached off NY Route 10 at East Delhi. World Guide Number 32-13- 02
Joe Nelson, P.O Box 267, Jericho, VT 05465-0267, jcnelson@together.netNo part of this web site may be reproduced without the written permission of Joseph C.
Nelson
Copyright © 2001, Phillip C. Pierce
Copyright © 2001, Bob &Trish Kane
This file posted March 13, 2001, revised November 5, 2001